6.3.1 Overview of program level data submitted
6.3.2 Time estimates for program activities
6.3.1 Overview of program level data submitted
A full six months of data was received from 43 out of 46 projects (94%), providing a total of 270 program data submissions for the period October 2012 to March 2013. The distribution of these submissions by month is shown in Table 6-3. The majority of projects submitted program level data for each of the six months from October 2012 to March 2013.Table 6-3: Program level data submission by month
Collection period | No. submitted | % total projects (n=46) |
---|---|---|
October 2012 | 46 | 100 |
November 2012 | 45 | 98 |
December 2012 | 45 | 98 |
January 2013 | 45 | 98 |
February 2013 | 46 | 100 |
March 2013 | 43 | 93 |
Total | 270 | - |
6.3.2 Time estimates for program activities
Program level data included estimates of the proportion of time spent by each project in relation to nine key activities, as follows:- Travel
- Event planning
- Administration
- Event/activity promotion
- Service provision
- Research and development
- Information development and provision
- Supervision
- Other
The minimum and maximum percentage range for each activity indicates that projects differed substantially in terms of the time spent in relation to each activity. Overall, service provision was, on average, the activity upon which projects spent most time (mean = 28.1%). However, it should be noted that some organisations were not involved in direct service provision, defined in the MDS Data Dictionary as time spent actually delivering services to individual or groups. Projects that allocated a greater proportion of their time to activities such as research and development or administration have low percentages allocated to service provision.
The time allocated to each activity is shown using 5% intervals in Table 6-5. The table identifies, for example, that 28 of the 270 program data submissions (over the six month period) report that travel time represented zero (0) percent of their time. Top of page
Table 6-4: Proportion of time allocation by program activity (%)
Program activity | Minimum % | Maximum % | Mean % |
---|---|---|---|
Travel | 0 | 60 | 11.2 |
Event planning | 0 | 75 | 13.7 |
Administration | 0 | 100 | 15.4 |
Event/activity promotion | 0 | 65 | 8.7 |
Service provision | 0 | 87 | 28.1 |
Research and development | 0 | 87 | 11.6 |
Information development and provision | 0 | 80 | 6.9 |
Supervision | 0 | 30 | 1.9 |
Other | 0 | 40 | 2.6 |
Table 6-5: Time allocation by program activity, all program data submissions
Time allocation (%) | Travel (n) | Event planning (n) | Administration (n) | Event/activity promotion (n) | Service provision (n) | Research (n) | Information provision (n) | Supervision (n) | Other (n) |
---|---|---|---|---|---|---|---|---|---|
0% | 28 | 29 | 11 | 32 | 65 | 82 | 164 | 215 | 205 |
1-5% | 82 | 60 | 43 | 112 | 10 | 90 | 45 | 26 | 26 |
6-10% | 70 | 70 | 75 | 75 | 20 | 39 | 21 | 19 | 21 |
11-15% | 39 | 32 | 47 | 19 | 15 | 7 | 3 | 6 | 3 |
16-20% | 22 | 23 | 46 | 17 | 14 | 15 | 10 | 1 | 8 |
21-25% | 5 | 23 | 16 | 5 | 12 | 6 | 1 | 1 | 4 |
26-30% | 12 | 14 | 9 | 4 | 20 | 5 | 4 | 2 | 1 |
31-35% | 7 | 7 | 10 | - | 16 | 1 | 3 | - | 1 |
36-40% | 3 | 4 | 6 | 5 | 31 | 5 | 9 | - | 1 |
41-45% | 1 | 1 | 3 | - | 7 | 1 | 2 | - | - |
46-50% | - | 5 | 1 | - | 12 | 1 | 3 | - | - |
51-55% | - | - | - | - | 2 | 1 | - | - | - |
56-60% | 1 | 1 | 2 | - | 23 | 5 | 1 | - | - |
61-65% | - | - | - | 1 | 8 | 1 | - | - | - |
66-70% | - | - | - | - | 2 | 1 | 1 | - | - |
71-75% | - | 1 | - | - | 1 | - | 2 | - | - |
76-80% | - | - | - | - | 3 | 5 | 1 | - | - |
81-85% | - | - | - | - | 8 | 3 | - | - | - |
86-90% | - | - | - | - | 1 | 2 | - | - | - |
91-95% | - | - | - | - | - | - | - | - | - |
96-100% | - | - | 1 | - | - | - | - | - | - |
Total | 270 | 270 | 270 | 270 | 270 | 270 | 270 | 270 | 270 |